R-22-19VILLAGE OF DEERFIELD
RESOLUTION NO. 2022- R-22-19
A RESOLUTION APPROVING A RENEWAL AGREEMENT WITH UNITED
METERS INC. OF MORRIS, ILLINOIS FOR
WATER METER HEAD REPLACEMENT SERVICES
WHEREAS, the Village of Deerfield ("Village') is a home rule municipality in
accordance with Article VII, Section 6 of the Constitution of the State of Illinois of 1970; and
WHEREAS, on December 21, 2020, the Village entered into an agreement with
United Meters Inc., of Morris, Illinois ("Consultant"), for the provision of Water Meter Head
Replacement services ("Agreement"); and
WHEREAS, pursuant to Section 02-52-00 of the Agreement, the Agreement may be
extended for up to two additional terms of one year; and
WHEREAS, the Village has been satisfied with the services provided by Consultant,
and desires to renew the Agreement through December 31, 2022, at rates consistent with the
provisions set forth in Paragraph 4.03 of the Agreement ("Renewal Agreement'); and
WHEREAS, the Mayor and Board of Trustees have determined that entering into the
Renewal Agreement with Consultant will serve and be in the best interest of the Village and
its residents;
NOW, THEREFORE, BE IT RESOLVED BY THE VILLAGE BOARD OF
DEERFIELD, LAKE AND COOK COUNTIES, ILLINOIS, as follows:
SECTION 1: RECITALS. The Village Board hereby adopts the foregoing recitals as
its findings, as if fully set forth herein.
SECTION 2: APPROVAL OF RENEWAL AGREEMENT. The Renewal
Agreement by and between the Village and Consultant is hereby approved in substantially
the form attached to this Resolution as Exhibit A, and in a final form and substance
acceptable to the Village Manager and the Village Attorney.
SECTION 3: AUTHORIZATION TO EXECUTE RENEWAL AGREEMENT. The
Mayor and the Village Clerk are hereby authorized and directed to execute and attest, on
behalf of the Village, the final Renewal Agreement upon receipt by the Village Clerk of at
least one original copy of the final Renewal Agreement executed by Consultant; provided,
however, that if the executed copy of the final Renewal Agreement is not received by the
Village Clerk within 60 days after the effective date of this Resolution, then this authority to
execute and attest will, at the option of the Mayor and Board of Trustees, be null and void.
SECTION 4: EFFECTIVE DATE. This Resolution shall be in full force and effect
from and after its passage and approval according to law.
100125506.11
AYES: Benton, Berg, Jacoby, Oppenheim, Seiden
NAYS: None
ABSTAIN: None
ABSENT: Metts-Childers
PASSED: March 21, 2022
APPROVED: March 21, 2022
RESOLUTION NO: R-22-19
LL�
Daniel C. Shapiro, Mayor
ATTEST:
Kent S. Street, Vi lage Clerk
{00125506.1 }
EXHIBIT A
Renewal Agreement
{00125506.11
Strand Associates, Inca'
910 West Wingra Drive
Madison, W 1 53715
_
(P) 608.251.4843
STRAND
ASSOCIATES"
March 4, 2022
CHANGE ORDER NO. 3 (2022 Phases 2, 3, and 4 Contract Extension)
PROJECT: Automated Meter Reading Equipment Installation
OWNER: Village of Deerfield, Illinois
CONTRACT: 1-2020
CONTRACTOR: United Meters, Inc.
Description of Change
3a Delete items 2a through 2j from Change Order No. 2.
(DEDUCT) ($189,866.00)
3b Item No. 1—General Conditions (add 1 each [EA] at
ADD
$3,000.00
$3,000/EA).
3c Item No. 2—Endpoint Non Pit Installation (add
ADD
$410,553.00
4,147 EA at $99/EA).
3d Item No. 3—Endpoint Pit Installation (add 419 EA at
ADD
$33,520.00
$80/EA).
3e Item No. 5-5/8-Inch (IN) Meter Pit Installation (add
ADD
$16,800.00
140 EA at $120/EA).
3f Item No. 7-3/4-1N Meter Pit Installation (add 118 EA at
ADD
$23,600.00
$200/EA).
3g Item No. I I —Section 33 19 00-Cash Allowance for
ADD
$6,000.00
Unique Meter and Endpoint Installation (add 1 lump
sum [LS] at $6,000/LS).
3h New Item No. C12-1.5-IN Meter Non Pit Installation
ADD
$1,825.00
(add 5 EA at $365/EA).
3i New Item No. C13-2-IN Meter Non Pit Installation
ADD
$9,375.00
(add 25 EA at $375/EA).
3j New Item No. C14-3-IN Meter Non Pit Installation
ADD
$9,520.00
(add 16 EA at $595/EA).
3k New Item No. C15-4-IN Meter Non Pit Installation
ADD
$11,000.00
(add 10 EA at $1,100/EA).
31 New Item No. C16-6-IN Meter Non Pit Installation
ADD
$7,275.00
(add 3 EA at $2,425/EA).
TOTAL VALUE OF THIS CHANGE ORDER:
ADD
$342,602.00
Contract Price Adjustment
Original Contract Price
$214,890.00
Previous Change Order Adjustments
$150,222.00
Adjustment in Contract Price this Change Order
$342,602.00
Current Contract Price including this Change Order
$707,714.00
JRB;tII\S:\MAD\1500--1599\1545\036\Construction\Change Orders\CO 3\CO 3.docx
Arizona I Illinois I Indiana j Ksnhicky E Ohio j Texas I Wisconsin
w\,vw.strand.com
Strand Associates,
Village of Deerfield, Illinois —United Meters, Inc.
Contract 1-2020, Change Order No. 3
Page 2
March 4, 2022
Contract Substantial Completion Date Adjustment
Original Contract Substantial Completion Date September 1, 2021
Contract Substantial Completion Date Adjustments due to previous Change Orders 455 Days
Contract Substantial Completion Date Adjustments due to this Change Order 0 Days
Current Substantial Contract Completion Dates including all Change Orders November 30, 2022
Contract Final Completion Date Adjustment
Original Contract Final Completion Date September 30, 2021
Contract Final Completion Date Adjustments due to previous Change Orders 457 Days
Contract Final Completion Date Adjustments due to this Change Order 0 Days
Current Final Contract Completion Dates including all Change Orders December 31, 2022
This document shall become a supplement to the Contract and all provisions will apply hereto.
RECOMMENDED
4 /Z- z Z-", 7 - - - 7/ q/.-2 ---)
EN/OINEER—Strand. Associates, Inc.0 Date
APPROVED
3 � 2oz2.
CONTRACTOR —United Meter , I c. Date
APPRO D
O NER Village o eer eld, Illinois Da
Jti[isU1�S:1AlAD`,1500--159e',I5-ISF03C,C'nnaudi.11\0-19e Ord.MCO ACO 3A, s
w%"v,stwnd.com