ORDINANCE NO. 0 -68- 49
AN ORDINANCE TO AMEND ORDINANCE NO. 0 -67 -56 ENTITLED:
"AN ORDINANCE PROVIDING FOR THE GRADING, PAVING,
DRAINING, AND OTHERWISE IMPROVING THE ROADWAY OF
HERTEL LANE AS EXTENDED FROM WILMOT ROAD TO CAROL
LANE, INCLUDING SIDEWALKS, WATER MAINS, SANITARY
AND STORM SEWERS,..IN THE VILLAGE.OF DEERFIELD,
LAKE AND COOK COUNTIES, ILLINOIS"
BE IT ORDAINED BY THE PRESIDENT AND BOARD OF TRUSTEES
OF THE VILLAGE OF DEERFIELD, LAKE AND COOK COUNTIES, ILLINOIS,
AS FOLLOWS:
,SECTION Ordinance No. 0- 67 -56, entitled "AN ORDINANCE
ONE: PROVIDING FOR THE GRADING, PAVING,.DRAINING,
,AND OTHERWISE IMPROVING THE ROADWAY OF HERTEL
LANE AS EXTENDED FROM WILMOT ROAD TO CAROL LANE, INCLUDING
SIDEWALKS, WATER MAINS, SANITARY AND STORM SEWERS, IN THE
VILLAGE OF DEERFIELD, LAKE AND COOK COUNTIES, ILLINOIS", hereto-
fore adopted by the President and Board of Trustees of the Village
of Deerfield on .the 18th day of September, 1967, is amended by
amending SECTION TWO thereof to read as follows:
"SECTION The recommendation of the Board of
TWO: Local Improvements providing for
the improvement and the supplemental
cost thereof, made by the President of the
Board of Local Improvements, both hereto
attached and made a part hereof, be and the
same are hereby approved."
SECTION All other provisions of Ordinance No. 0 -67 -56
TWO: shall remain in full force and effect.
SECTION This Ordinance shall be in full force and effect
THREE: from and after its passage and approval thereof.
AYES: SIX (6
NAYS: NONE (0)
ABSENT: NONE (0)
PASSED this _ 16W; ..__ day of . SeRte ber A.D'. 1968
APPROVED this 16th day of September A ".D'. 1968
ATTEST:
r Village Preside
r
RECOMMENDATION BY THE BOARD OF LOCAL
IMPROVEMENTS OF THE VILLAGE OF DEERFIELD,
LAKE COUNTY, ILLINOIS, TO THE BOARD OF
TRUSTEES OF THE SAID VILLAGE OF DEERFIELD,
FOR THE PASSAGE OF AN ORDINANCE AMENDING
AN ORDINANCE,PROVIDING'FOR A LOCAL IMPROVE-
MENT
TO: President and Board of Trustees
Village of Deerfield
i Lake County, Illinois
We herewith submit an Ordinance Amending an Ordinance
providing for the making of a Local Improvement entitled as
follows:
"AN ORDINANCE PROVIDING FOR THE GRADING, PAVING,
DRAINING AND OTHERWISE IMPROVING THE ROADWAY
OF HERTEL LANE AS EXTENDED FROM WILMOT "GOAD TO
CAROL LANE, INCLUDING SIDEWALKS, WATER MAINS,
SANITARY AND STORM SEWERS, IN THE VILLAGE OF
DEERFIELD, LAKE AND COOK COUNTIES.; ILLINOIS"
together with a Supplemental Estimate of the cost of said
Improvement and recommend the passage of said Ordinance and
the making of the Improvement contemplated thr.rein.
Respectfully-submitted,
BOARD OF LOCAL IMPROVEMENTS,
DEERFIELD, ILLINOIS
President
Member
Member
Member
ember
ATTEST:
Member
2
March 31,
1967
..;
rile 1,11226
Revised W1 ay. 3, 1967
SUPPLEMENTAL
PRESIDENT.' -S :- COST ESTIMATE FOR
•HE�tTE.L I.ANE: S.A. 106, DEERFIELD, ILLINOIS
Item
No.. Quantity
Item
Amount
-A. GRADING &
PAVING
C, Y. of Excavation for the Non - Reinforced
P. C, C. Pavement 'with an integral curb,
driveway replacement. The parkways,
including the removal &disposal of all earth
.-all sub - grading & compacting, furnishing
& placing of all borrow that may be required,
.".—Placing of al.l fill, removal of.al.l existing
'
pavement including base &• Surface Courses,
curbs, &' gutters, combined curb & gutters„
• 'driveways, & the removal & disposal of all
l.og, skimps, brush; 'trees under six' (6 ")
.,inch diameter, 'vcgrtation, rubbish &other:
objectionable matters complete in place
at $1.75 per C. Y.
.$2.,292.50
.2, 1,.326".
S'. Y. Non - reinforced 'P. C. C. Pavement
6 "_,,thick with integral curb, including
,' .longitudinal, transverse and expansion
joints, complete at $5:.25 per S. Y.
6,930.00
.3. " 5, 400 .'
S, F. P, C. C. Sidewalk'4" thick and all
znatorials, placing, finishing, backfilling
and expansion joints, .complete in place
i
at $0. 65 per S. F.
3,510.00
4, 630:
S. P. P.C. C. Driveway 1) avcrnent, 6"
thick, and all materials, Placing, finishing
,
backfilling and expansion joints, complete
in place at $0. 80 per S. F.
544.00
5.. 230.
S. Y. crushed stone surface course Type D
Grade 8, 6" compacted thickness, for drive-
.
ways, including placing, spreading compacting
and leveling complete in place at $2. 15 per
S.F.
$ 494..50
Sub Total for Grading and'Paving:
$13.,771...00
2
Amount
$1,787.50
54.00
121.50
150.00
300.00
$2,713.00
Item
No. Quantity
Item
B. STORM DRAINAGE
1. 325
L. F. '12" Storm Sew,,r ASTM Designation
C -76, Class III Complete in Place at
$5. 50 per L. F.
2. 9'
L. F. 12" Storm Sewer ASTM Designation
C -76, Clas.s III Inlet Connection Complete
'
'in Place at - $6. 00 per L. F.
3. 27
.L. F. 10" Storm Sewer ASTM Designation
C -76 Clas.s III Inlet Connections complete
in Place at $4, 50 per L,,F,
4, 1
Each, Concrete Inlet; 24" I, D. , 5" Wall
thickness on 4" concrete foundation, incl-
uding all labor and materials, excavation
and removal of surplus material and
standard-frame and grate complete in
place at $150.00 Each
5. 1
Each Concrete Inlet Catch Basin, 48" I. D.
5" Wall Thickness, on 6" concrete founda-
tion, with sunip as shown on plans,
including all labor and materials, excavation
and removal of surplus material. and
standard frame and grate complete in place
at $300.00 Each
6. 1
Each Concrete Manhole 48" I, D., =. Wall
Thickness, on 6" concrete founda:i:, :: with
moulded inverts, including all labor: and
materials, excavation and removal of
surplus material and standard frarn—, and
cover complete in place at $300.00 :ach
Sub Total for Drainage Construction:
' fil
-3-
Amount
$1,787.50
54.00
121.50
150.00
300.00
$2,713.00
0
- 4
Item
No. Quantity
Item
Amount'.
C. SANITARY SEWERS:
1. 315 •
L. F. of V. C..P. 8" diameter, ASTM
Designation, C -200, with C -425 Type III
joints, including excavation, laying,
hackfilling and disposal of surplus excava-
ted material, complete in place at
$5.00 per L.F.
$.19575.00
2. 2
Each Precast Concrete Manholes, 48"
I. D., 5" Wall thickness, on 6" concrete
-foundation with moulded inverts, including
all labor and materials, excavation and'
removal of surplus material and standard
frame and cover, complete in place at
$350.00 Each
700.00
3. 5
Each 6" V. C. 1'. ASTM Designation C -200
with Type III .joints, House service, laid
complete to property line including excava-
tion, laying, backfilling, removal of surplus
materials at $150.00 Each
750:.00
Sub Total for Sanitary Sewers:
$3,025:00
0
- 4
TOTAL ESTIMATED COST OF- IMPROVEMENT: $29,646..61,
President Board of-Local Improvements
Item
No. Quantity Item
Amount
D. ' WATER SUPPLY
1. 657 L, F. of 6" I. D. Bell and Spigot, CIWM
laid- complete with ring tight couplings or
equal in all excavation, connection
to existing or proposed mains, select
backfill, .removal of all surplus excavated
material, sterilization of main and pressure
testing at $4.50 per. L. F.
$3,037.50
.1 Each, Fire Hydrant complete with
,
auxiliary valve and all necessary labor
and material to install at $425. 00 Each
425-00
3, 1 Each, 6" Pressure Tap, including construction
of valve and vault to he made at casting
10 ". main, taking all necessary precautions,
constructed complete at $600. 00 Each
600.00
4. 5 Each 3/4" Copper water pipe, Type K,
house services with tap, corporation cock,
round way and buffalo box, laid complete to
property line including excavation, laying,
backfilling, and removal of surplus material
at $150. 00 Each
750.00
Sub Total Waterma'in:
$4',812.50
.Total Estimated Cost of Construction
$24,321.50
Cost of Engineering, Inspection and 'Quality Control
$' 3,647.00
TOTAL:-. ,
$27,968,50
All lawful expenses attending the proceedings for making
said improvements, including the court costs and the making,
levying and collection-of the assessment of said improvement, not
in excess of six (6) percent of the cost of said improvement.
$1', 678.1-L
TOTAL ESTIMATED COST OF- IMPROVEMENT: $29,646..61,